Section 38 agreement - adoption of highways
Section 38 of the Highways Act 1980 provides that when planning consent has been granted for a new development, developers may ask the highway authority to ‘adopt’ new roads that have been constructed as part of the development, along with associated infrastructure such as drains, lighting and supporting structures.
Adoption means the highway authority agrees to undertake maintenance of the road from an agreed date at the public expense. The agreement between the highway authority and the developer is called a Section 38 Agreement.
The highway authority will be either the Secretary of State for Transport or the local highway authority.
Before entering into an agreement, the developer must have obtained planning permission, including approval of any reserved matters. The planning permission will generally include an indicative layout of the roads to be adopted.
The Section 38 Agreement may contain:
- Details of the relevant planning permission.
- Drawings indicating the extent of the area to be adopted.
- Provision for land dedication.
- Technical drawings of the works needed to be carried out.
- A programme for the works and for the adoption.
- Provision for inspection and certification of the works.
- Agreement regarding the adoption, or not, of supporting structures.
There will be a fee associated with the agreement, covering the cost of; checking designs, preparing the agreement, inspecting the works, and ongoing maintenance of items not essential for highway purposes (commuted sums). There may also be a requirement for a bond from the developer to cover the highway authority against the possibility that the developer fails to properly complete the works, for example if they become insolvent.
The works must be constructed to a design and standard agreed by the highway authority. The developer will be responsible for carrying out the works at their own expense, and for maintenance costs until adoption.
There will generally be a 12 month maintenance period between the completion of the works and the adoption of the roads. If the development is phased, then adoption will generally take place after the final phase is completed. This is because the roads may continue to be used as a means of access by construction traffic.
The procedure necessary to reach agreement can be time consuming and protracted, and so it is desirable to enter into discussion with the highway authority as early in the project as possible.
Section 38 Agreements are often entered into alongside Section 278 Agreements, which allow developers to carry out works to a public highway. This may be necessary, for example, to provide access to a new site or to improve access to an existing site. See Section 278 Agreement for more information.
NB: Section 37 of the Highways Act 1980 enables developers to offer completed roads to the highway authority for adoption. This is generally considered a less desirable route than a Section 38 Agreement.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Adopted highway.
- Community Infrastructure Levy.
- Highways.
- Highway infrastructure and local authorities.
- Manual of Contract Documents for Highway Works.
- Planning condition.
- Planning obligation (Section 106 Agreement).
- Planning permission.
- Reserved matters.
- Section 50 agreement.
- Section 184 agreement.
- Section 215.
- Section 278 Agreement.
[edit] External references.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.